水穩(wěn)攤鋪施工過程需要注意的事項
來源:http://guixin.net.cn/ 日期:2023-06-16
混合料的拌和
Mixing of mixtures
濟南水穩(wěn)砼廠家提醒您,在開始拌合前,拌合場的備料應(yīng)滿足3~5天的攤鋪用料。每天開始攤鋪前,應(yīng)檢查場內(nèi)各處集料的含水量,計算當日的配合比,外加水與天然含水量的總和要比佳含水量略高1個百分點。
Jinan water stabilized concrete manufacturer reminds you that before starting mixing, the material preparation at the mixing plant should meet the paving requirements of 3-5 days. Before starting paving every day, the moisture content of the aggregates in various parts of the site should be checked, and the mix ratio for that day should be calculated. The total amount of added water and natural moisture content should be slightly higher than the optimal moisture content by 1 percentage point.
每天開始攪拌之后,出料要檢查是否符合設(shè)計配合比,進行正式生產(chǎn)之后,每1~2小時檢查一次拌合情況,抽檢其配合比、含水量是否變化。
After starting mixing every day, the discharge should be checked for compliance with the designed mix ratio. After formal production, the mixing condition should be checked every 1-2 hours, and the mix ratio and water content should be randomly checked for any changes.
高溫作業(yè)時,早晚與中午的含水量要有區(qū)別,要按溫度變化及時調(diào)整。拌合機出料不允許采取自由落地、裝載機裝料運輸?shù)霓k法,采用由漏斗出料直接裝料運輸。裝車時車輛應(yīng)前后移動,分三次裝料,避免混合料離析。
During high-temperature operations, there should be a difference in water content between morning and evening and noon, and adjustments should be made in a timely manner according to temperature changes. The method of free landing and loading and transportation by loader is not allowed for the discharge of the mixer, and direct loading and transportation by funnel discharge is adopted. When loading, the vehicle should move forward and backward, loading in three stages to avoid segregation of the mixture.
混合料的攤鋪
Spreading of mixture
攤鋪前應(yīng)將下層適當灑水潤濕。混合料運施工現(xiàn)場后,采用攤鋪機攤鋪的方法按照掛設(shè)的高程控制線進行攤鋪。掌握好松鋪厚度與壓實后厚度的關(guān)系,進而嚴格控制好水穩(wěn)層的壓實厚度和高程,確保壓實厚度滿足設(shè)計要求。好是配備基于北斗定位的智能攤鋪系統(tǒng),可以大大提高工程質(zhì)量以及降低人工成本。
Before paving, the lower layer should be properly moistened with water. After the mixture is transported to the construction site, it is spread using a paver according to the elevation control line set up. Master the relationship between the loose paving thickness and the compacted thickness, and strictly control the compacted thickness and elevation of the water stable layer to ensure that the compacted thickness meets the design requirements. The good thing is to equip an intelligent paving system based on Beidou positioning, which can greatly improve project quality and reduce labor costs.
混合料的碾壓
Rolling of mixture
攤鋪后壓路機應(yīng)及時進行碾壓。一次碾壓長度一般為50m左右。穩(wěn)壓要充分,振壓不起浪花、不推移。壓實時,可以先穩(wěn)定(遍數(shù)適中,壓實度達到85%)→開始輕振動碾壓→再重振動碾壓→后穩(wěn)壓,壓無輪跡為止。碾壓過程中,可用灌砂法檢測壓實度,不合格時,重復(fù)再壓(注意檢測壓實時間)。直碾壓壓實度合格為止。
After paving, the roller should be rolled in a timely manner. The length of one compaction is generally about 50m. The voltage stabilization should be sufficient, and the vibration pressure should not cause waves or movement. When compacting, it is possible to first stabilize (with a moderate number of passes and a compaction degree of 85%), then start light vibration compaction, then heavy vibration compaction, and then stabilize until there are no wheel marks. During the compaction process, the sand filling method can be used to test the compaction degree. If it is not qualified, repeat the compaction (pay attention to the compaction time). Until the compaction degree is qualified.
水穩(wěn)攤鋪施工過程需要注意的事項就講解到這里了,希望能夠給您好的幫助,更多事項就來我們網(wǎng)站http://guixin.net.cn咨詢吧!
That's all we need to pay attention to during the construction process of water stabilized paving. We hope to provide you with good help. For more details, please visit our website http://guixin.net.cn Consult!